Silvercorp raises El Domo project budget to $298.2M, delays production to Nov 2027 due to cost increases and weather.
Silvercorp Metals updated the El Domo project construction budget to $298.2 million, up $14.6 million from earlier estimates, mainly due to higher diesel prices, enhanced water management, and power supply needs. Heavy rainfall linked to Super El Nin...