Silvercorp raises El Domo Project budget to $298.2M, delays production to Nov 2027 due to fuel costs and heavy rain.
Silvercorp Metals updated the El Domo Project construction budget to $298.2 million, up $14.6 million from February 2026, mainly due to increased diesel prices and additional water management work caused by heavy rainfall. The project completion is d...